Proof of Progress45 mins ago
Modern Kitchen Renovation
For:The Anderson Family
Progress0%
StatusOn Track
CompletionSep 16, 2026
Budget$21.7K of $35K
01
Design & Planning
DoneFinalize kitchen layout, materials, and fixtures
Completed May 30, 2026
02
Demolition
DoneRemove existing cabinets, countertops, and flooring
Completed Jun 6, 2026
03
Rough-In Work
DoneElectrical, plumbing, and HVAC rough-in for new layout
Completed Jun 28, 2026
04
Drywall & Paint
In progressInstall and finish drywall, prime and paint walls
ETA: Jul 22, 2026
05
Flooring Installation
Install luxury vinyl plank flooring
Starts Jul 23, 2026
Duration: 3 days
06
Cabinet Installation
Install base and upper cabinets, kitchen island
Starts Jul 27, 2026
Duration: 5 days
07
Countertop Fabrication & Install
Template, fabricate, and install quartz countertops
Starts Aug 3, 2026
Duration: 1 week
08
Tile Backsplash
Install subway tile backsplash with custom grout
Starts Aug 16, 2026
Duration: 3 days
09
Fixtures & Appliances
Install sink, faucet, lighting, and appliances
Starts Aug 21, 2026
Duration: 4 days
10
Final Touches & Walkthrough
Hardware, trim work, final cleaning, and client walkthrough
Starts Sep 11, 2026